Monday, July 20, 2026 -Jigawa State Governor Umar Namadi has ordered the immediate suspension of the N1.3 billion contract for the renovation and remodelling of Gumel General Hospital.
The decision followed an unscheduled late-night inspection
of the facility, during which the governor assessed the quality and pace of
work at critical sections of the hospital, including the male and female wards,
the General Out-Patient Department, and the isolation centre.
The governor expressed his dissatisfaction with the
contractor’s performance and ordered the immediate suspension of the project.
Governor Namadi said the work carried out so far did not
reflect the scope of the contract awarded by the state government, describing
the progress as unsatisfactory.
According to him, the project was intended to deliver a
comprehensive renovation and remodelling of the hospital, but the execution had
failed to meet the government’s expectations.
“The progress of the work is unacceptable. We approved a
complete renovation and remodelling of the hospital, but what we have seen does
not meet the agreed standard. I have therefore directed that the project be
suspended while we review the situation with the contractor,” the governor
said.
He directed the Ministry of Health to suspend the contractor
and take the necessary measures to protect public funds while ensuring the
project is completed in line with the approved specifications.
The renovation contract, valued at more than N1.3 billion,
was awarded to Yasmeen Automobile Nigeria Limited on December 17, 2025, with an
eight-month completion timeline. However, seven months after work commenced,
the governor said the level of execution remained far below expectations.
He reiterated that his administration would not condone
poor-quality projects, warning contractors handling government contracts that
strict adherence to specifications, quality standards and timely delivery
remains non-negotiable.
Governor Namadi also visited Ringim General Hospital, where
he inspected ongoing renovation work and instructed the contractor to address
the identified shortcomings and accelerate the pace of execution.